What Is Construction Backlog?
Construction backlog represents contracted work that has not yet been completed.
For contractors, backlog can provide visibility into future:
revenue;
gross profit;
staffing needs;
equipment requirements;
project timing; and
working-capital demands.
A healthy backlog can be a strong indicator of future activity.
But backlog is not simply future revenue.
It is also a commitment to perform future work.
Why Backlog Matters
Backlog helps leadership understand what work is already under contract and still needs to be completed.
That can support decisions around:
hiring;
project management;
estimating;
cash flow;
bonding;
banking;
equipment; and
growth.
The key question is not simply:
“How much backlog do we have?”
It is:
“What does that backlog mean financially and operationally?”
A Simple Backlog Example
Suppose a contractor has:
Total contract value: $20 million
Revenue recognized to date: $8 million
Remaining contracted work:
$12 million
That remaining $12 million may represent backlog, depending on the contractor's reporting methodology and contract circumstances.
The number provides visibility into future work that has already been secured.
Backlog Is Not the Same as Revenue
Backlog represents work that remains to be performed.
Revenue reflects work that has already been earned under the applicable revenue-recognition method.
A project can therefore have:
Contract value: $5 million
Revenue earned to date: $2 million
Remaining backlog: $3 million
The contractor has not yet earned that remaining $3 million.
It still has to perform the work.
Backlog Is Not the Same as Cash
Backlog also does not mean the contractor has cash coming immediately.
Before that backlog becomes cash, the company may need to:
perform work;
incur costs;
submit billings;
wait for approvals; and
collect from the customer.
A large backlog can therefore create significant working-capital demands.
Backlog Should Include Expected Gross Profit
Revenue alone does not tell leadership whether the backlog is attractive.
Two contractors may each report:
$20 million of backlog
But one may expect:
$4 million of gross profit
while the other expects:
$2 million.
The economics are very different.
Management should understand both:
backlog revenue
and
backlog gross profit.
Track Backlog Margin
A useful metric is expected gross margin on backlog.
For example:
Backlog: $10 million
Expected gross profit: $1.8 million
Expected backlog gross margin:
18%
That helps leadership evaluate the quality of future work—not simply the quantity.
Backlog Quality Matters
A large backlog can look impressive.
But management should understand what is inside it.
Important considerations include:
expected margin;
customer quality;
contract terms;
project complexity;
geographic concentration;
retainage;
bonding requirements; and
payment timing.
A smaller, higher-quality backlog may be more valuable than a larger, weaker one.
Timing Matters
Backlog should be analyzed by expected timing.
For example:
Total backlog: $18 million
Expected over next 3 months: $8 million
Expected months 4–6: $6 million
Expected beyond 6 months: $4 million
That profile has different implications than $18 million spread evenly over two years.
Timing affects:
staffing;
payroll;
cash;
equipment; and
project-management capacity.
Backlog Burn Measures How Quickly Work Converts
Backlog burn refers to how quickly existing backlog is expected to convert into revenue.
A contractor with:
$24 million of backlog
may appear well positioned.
But if most of it is scheduled to be completed within six months, leadership may face:
significant staffing needs;
high material purchases;
increased subcontractor payments; and
short-term working-capital pressure.
Backlog timing is as important as backlog size.
Project Concentration Matters
Backlog can be risky when too much is concentrated in one project.
For example:
Total backlog: $20 million
Largest project: $9 million
That single project represents:
45% of backlog.
If that project experiences:
delays;
margin fade;
payment disputes; or
cancellation risk,
the effect on the company may be material.
Customer Concentration Matters Too
A contractor may have multiple projects but still be heavily dependent on one customer.
For example:
Top customer: 50% of backlog
Top three customers: 75% of backlog
That concentration should be understood.
Customer-specific risk can affect:
future revenue;
collections;
cash flow; and
overall business stability.
Track Backlog by Market or Sector
Some contractors may also benefit from tracking backlog by:
public vs. private;
commercial vs. residential;
customer type;
geography;
service line; or
project type.
That can help leadership understand diversification and strategic exposure.
Backlog Creates Staffing Requirements
Future work requires people.
Management should translate backlog into expected:
field labor;
project managers;
estimators;
superintendents;
finance support; and
administrative capacity.
A contractor can have a financially attractive backlog and still struggle if it lacks the people to execute it.
Backlog Creates Equipment Requirements
Projects may require:
vehicles;
heavy equipment;
tools;
temporary facilities;
technology; or
specialized assets.
Those needs should be considered before the work begins.
Equipment decisions can affect:
cash;
debt;
leverage; and
profitability.
Backlog Creates Working-Capital Needs
More work typically means more:
payroll;
materials;
subcontractor payments;
mobilization;
insurance; and
overhead.
If customer collections lag, the contractor may need to finance those costs.
That means a growing backlog can consume working capital.
Related Resource: What Is Working Capital and Why Does It Matter to Contractors? →
Backlog Growth Can Outpace Cash
Suppose backlog increases from:
$10 million
to
$25 million
in six months.
That may be excellent from a sales perspective.
But leadership should ask:
Do we have enough working capital?
Can the bank support us?
Do we have enough bonding capacity?
Will payroll materially increase?
Are materials needed upfront?
Do we have enough project managers?
Backlog growth without financial planning can create liquidity pressure.
Backlog Should Feed the Cash Forecast
Backlog is an important input into forward-looking cash planning.
For each major project, consider:
start date;
expected billings;
expected collections;
payroll;
materials;
subcontractors;
retainage; and
estimated completion.
That helps convert backlog into a projected cash profile.
Related Resource: How Should a Contractor Forecast Cash Flow? →
Backlog Should Feed the 13-Week Forecast
Projects beginning within the next several weeks should appear in the contractor's near-term cash forecast.
If three major projects mobilize in the same month, the company may experience:
higher payroll;
material deposits;
subcontractor mobilization; and
additional overhead
before collections catch up.
Related Resource: What Is a 13-Week Cash-Flow Forecast for a Contractor? →
Backlog and WIP Should Connect
Backlog and WIP are closely related.
WIP typically helps management understand active projects.
Backlog helps show the portion of contracted work that remains.
The reports should tell a consistent story.
For example:
contract values should align;
expected margins should be explainable;
project completion should be supportable; and
remaining work should reconcile with management's expectations.
Related Resource: What Is a Construction WIP Schedule? →
Backlog Can Reveal Future Margin Risk
If backlog has a lower expected margin than current work, future company profitability may decline.
For example:
Current gross margin: 20%
Expected backlog margin: 14%
That six-point difference could materially affect future earnings.
Leadership should understand the future margin embedded in the pipeline.
Backlog Can Also Improve Visibility
A strong backlog may provide management with more confidence around future revenue than a business relying primarily on short-term or uncommitted work.
That visibility can help with:
budgeting;
hiring;
capital planning; and
forecasting.
But the quality and timing of backlog still matter.
Backlog Is Different From Pipeline
Backlog generally relates to work already under contract.
Pipeline may include:
bids submitted;
proposals outstanding;
negotiated opportunities;
potential change orders; and
other work not yet secured.
Those categories should not be mixed.
A $10 million signed backlog is very different from a $10 million sales pipeline.
Separate Signed Work From Probable Work
Management dashboards should clearly distinguish:
Contracted backlog
from
probable or prospective work.
That prevents planning decisions from being based on revenue that has not yet been secured.
Change Orders Can Affect Backlog
Approved change orders may increase:
contract value;
remaining work;
expected revenue; and
backlog.
Pending change orders require more judgment.
Contractors should avoid overstating backlog with amounts that are not sufficiently approved or supportable.
Related Resource: How Should Contractors Account for Change Orders? →
Cancellations and Scope Changes Can Reduce Backlog
Backlog is not always permanent.
Projects may:
be canceled;
delayed;
reduced in scope;
terminated; or
materially modified.
Management should periodically reassess whether reported backlog still reflects realistic future work.
Backlog Should Be Updated Regularly
For active contractors, backlog should generally be refreshed as part of the recurring financial-management process.
Updates may include:
new contracts;
completed work;
approved change orders;
revised project schedules;
contract reductions; and
project cancellations.
Stale backlog creates poor forecasts.
Track Backlog by Project Manager
Depending on the company, leadership may track backlog by project manager.
That can show:
workload;
concentration;
expected gross profit; and
capacity.
A project manager responsible for significantly more work than peers may face execution risk.
Track Backlog by Expected Completion Date
This helps management identify periods of concentrated workload.
For example:
Q1 backlog burn: $5 million
Q2: $9 million
Q3: $3 million
Q2 may require materially more:
labor;
equipment;
subcontractors; and
cash.
Use Backlog in the Annual Budget
A construction budget should not begin only with a top-down revenue target.
Backlog can provide a bottom-up starting point.
Management can identify:
revenue already under contract;
expected timing;
expected gross margin; and
remaining revenue needed from new work.
That improves budgeting discipline.
Backlog Helps Frame the Revenue Gap
Suppose next year's revenue target is:
$30 million
Existing backlog expected to convert next year:
$21 million
The contractor has approximately:
$9 million of additional revenue
that must come from:
new contracts;
service work;
change orders; or
other sources.
That is a much clearer sales and estimating target.
Backlog Should Be Stress-Tested
Leadership should consider what happens if:
projects start late;
customer approvals slow;
margins decline;
a major project is canceled; or
collections are delayed.
A forecast built entirely on the assumption that every project occurs exactly as planned may overstate financial capacity.
Backlog Can Affect Bonding
Sureties may evaluate:
total backlog;
project concentration;
gross margin;
WIP;
working capital; and
financial capacity
when considering future bonding.
A large backlog may be positive.
But it may also indicate substantial future obligations.
Related Resource: What Does a Surety Look for in a Contractor's Financial Statements? →
Backlog Can Affect Banking
Banks may also care about backlog when evaluating:
future revenue;
line-of-credit needs;
working capital; and
repayment capacity.
A contractor projecting rapid backlog growth may need to discuss financing requirements before the work begins.
Backlog Should Be Discussed With Operations
Accounting should not maintain backlog in isolation.
Useful input may come from:
project managers;
estimating;
operations;
sales; and
leadership.
Operations knows when the work is expected to occur.
Finance translates that timing into:
revenue;
margin;
cash; and
working-capital requirements.
A Practical Backlog Dashboard
A useful backlog dashboard may include:
total backlog;
expected backlog revenue by month;
expected backlog gross profit;
backlog gross margin;
largest project;
largest customer;
project concentration;
backlog by project manager;
backlog by sector;
expected completion timing; and
change from prior month.
The goal is to make future work understandable.
Questions Leadership Should Ask
A recurring backlog review should answer:
How much work is under contract?
When will it be performed?
What gross profit is expected?
Which projects are largest?
Which customers represent the most exposure?
Are margins changing?
What staffing is required?
What equipment is required?
What working capital will be needed?
Can the current finance and operating team support the workload?
Those questions turn backlog into a planning tool.
Common Backlog Mistakes
Common contractor mistakes include:
treating backlog as guaranteed profit;
confusing backlog with pipeline;
tracking revenue but not margin;
ignoring timing;
overlooking customer concentration;
overlooking project concentration;
failing to update for change orders;
ignoring working-capital requirements;
not connecting backlog to staffing; and
not linking backlog to cash forecasting.
A large backlog is only useful if the company can execute it.
The Bottom Line
Construction backlog represents contracted work that has not yet been completed.
A healthy backlog can provide valuable visibility into future:
revenue
gross profit
staffing
project timing
and
growth.
But backlog also creates future obligations.
Leadership should understand:
how much work is coming
when it will occur
how profitable it is expected to be
how concentrated it is
and
how much cash and working capital it will require.
Backlog is not simply a sales metric.
Used correctly, it is a financial-planning and operational-capacity tool.
How Bilotta & Company Can Help
Bilotta & Company, CPAs, LLC works with construction contractors on backlog analysis, WIP reporting, job costing, budgeting, cash-flow forecasting, working-capital planning, accounting, tax, assurance, and financial leadership.
Through our Contractor Compass® Financial Stewardship program, we help contractors connect:
backlog
project margins
cash flow
working capital
staffing
and
growth decisions.
Our Financial Stewardship as a Service® rhythm is:
Close → Analyze → Forecast → Decide.
Backlog becomes much more useful when it moves from a number on a report to a clear view of what the business needs to execute next.
Related Resource: What KPIs Should a Construction Company Track? →
Related Resource: How Does Growth Affect Construction Cash Flow? →
Related Resource: What Is a Construction WIP Schedule? →
Visit the Construction Contractor Financial Resource Center →
This article is provided for general educational purposes and should not be considered accounting, tax, legal, bonding, lending, estimating, or financial advice for a specific contractor. Backlog calculations, reporting practices, and planning assumptions may vary based on contract terms, business model, accounting policies, and other circumstances.